Banks, ACT
The asset will be held by the borrower as an investment for the duration of the facility.
Morwell & Tatura, VIC
Tatura:
• There have been 44 settlements achieved to date in Stage 2, with an additional 3 sold. Koham Property are actively marketing the remaining 11 lots from Stage 1 and 2.
Morwell:
• Civil works on the project are ongoing for Stages 1-3.
• Forecast from Winslow is unchanged, with PC expected for Stages 1, 2 & 3 in Mar-26, Apr-26 and May-26 respectively.
• 62 presales have been achieved across Stages 1-3 of the project, with an additional 9 achieved for Stage 4.
The facility remains in default, and ARK has reserved its rights from the 7 March 2025 expiry to charge default interest until an acceptable resolution or exit is reached with the borrower.
Ballarat North, VIC
No further updates have occurred since the property’s exclusion from the Ballarat North PSP, apart from an adjustment to the facility to maintain covenant compliance.
Mount Cottrell, VIC
The borrower continues to hold the properties as a land bank. The due diligence period on the Oakbank PSP has been completed. The VPA has submitted the 2025/2026 business plan to the Minister for Planning which includes prioritisation of Horizon 2 PSPs. There is potential for the Oakbank PSP to be included in the business plan, while no official timeframe for approval has been provided.
Gungahlin, ACT
Sellicks Beach & Gilberton, SA
The remaining allotments from Sellicks Beach have been refinanced into a residual stock facility secured against five remaining residential lots and two commercial allotments at a 75% LVR.
Following financial close, two of the five residential lots have sold and settled, with the remaining three currently pending settlement, leaving the two commercial allotments.
Buckingham Arms is expected to be refinanced in early February 2026.
Newport, NSW
The facility, which expired on 28 July 2025, remains in default, with interest continuing to capitalise until repayment.
Civil works on site have now been completed, with titles forecast to be registered in March 2026.
The Marina DA continues to progress, albeit slowly, with a resolution currently expected by March 2026.
Gawler, SA
Across Stages 5–7, and including Stages 8–9, more than 95% of lots have now been sold. While the facility relates only to Stages 5–7, sales across the broader project have remained strong.
Civil works for Stages 5–7 continue to progress, with completion currently now forecasted for Q2 2026.
Munno Para Downs (Smitham Road), SA
- Retaining wall installation is underway
- Rubble pavement construction is in progress
- Stormwater pipe installation is underway
- Gabion wall installation is in progress
- Headwall installation is underway
Shepparton North, VIC
Settlements continue to occur within the Stage 1 and 2 residual stock facility.
The Stage 3 construction facility has been refinanced into a residual stock facility.
Bulk earthworks for Stage 4 have been completed, and sewer and drainage works have since commenced.
Burpengary, QLD
Munno Para Downs (Andrews & Hatcher Road), SA
Elizabeth South, SA
The original construction facility has been restructured into two residual stock facilities to reflect the separate ownership of the remaining allocated lots.
Four settlements were achieved during the month, with two fully repaying the construction facility and the remaining two applied toward reducing the residual stock facilities.
Devon Park, SA
Remediation works have been completed, with all soil and vapour validation results returned within the required limits. The audited remediation report has now been issued to the EPA for acceptance.
Civil works commenced in December 2025 and are currently in progress.
Cowaramup, WA
The borrower continues to finalise the detailed design and execute the civil works contract to enable the project to progress into the construction phase.
New Farm, QLD
Morwell, VIC
The development manager has taken over management of sales and marketing activities for the project. They are currently reviewing submissions from both local agents and larger firms, including Knight Frank. Interviews are underway, and following this process, a new sales agent is expected to be appointed to help drive increased sales activity.
Hackney, SA
Settlement of the West Lakes property is now forecast for early February 2026. Following settlement, it is expected that the hotel and the remaining Skyloft apartments will be refinanced with a major bank or alternative lender, supported by the hotel now being fully operational.
The hotel is currently operating under a 3-year lease with Urban Rest as the hotel operator.
Warragul, VIC
Due to delays in receiving the planning permit, the facility will be extended by a further three months to provide the borrower with additional time to complete the construction tender process, finalise engineering, and commence sales and marketing.
Windsor & Prahran, VIC
The borrower continues to hold the property as an investment asset.
Mackay, QLD
The borrower continues to work with council in preparation for securing the planning permit.
Athol Park, SA
The development approval was obtained on 17 December 2025. A sales campaign has been launched on commercial real estate platforms, with CBRE appointed as the selling agent. The borrower is currently preparing to commence construction.
Waterloo Corner, SA
The Approval Package, including the engagement report, has been submitted to the Minister of Planning’s department. The Code Amendment will be further progressed once the Interim Infrastructure Agreements are finalised by the Government’s Growth Infrastructure Coordination Unit.
Toowong, QLD
The borrower continues to work with council to progress the planning application.
Gawler Belt, SA
Planning consent was granted on 2 December 2025, followed by building consent on 19 December 2025. Construction funding was activated upon receipt of the required approvals. Civil works are underway, including survey and footings, with the quantity surveyor forecasting practical completion on 3 November 2026.
Deanside, VIC
To date, 5 presales have been secured, with additional sales anticipated in the coming month. Construction is approaching commencement and is on schedule to start before the end of February.
Moe, VIC
The project is progressing in line with expectations, with the majority of trade packages close to being fully locked in. The borrower intends to register a plan of consolidation to merge the two properties into a single title and establish a drainage easement, to which Ark has provided consent. The first construction drawdown is anticipated in March 2026.
Wakefield, SA
The construction facility reached financial close in December 2025. The project will deliver an 18-storey mixed-use building featuring ground-floor retail, 120 co-living apartments across Levels 2–9, and a 120-room hotel/short-term accommodation. Preparation for construction readiness is underway.
North Beach, SA
Sewer works are currently underway, with vegetation clearance and grubbing completed.
Mount Rascal, QLD
The facility reached financial close last month. A more comprehensive update will be provided next month.