Banks, ACT
The facility is expected to be refinanced into a new 12-month facility next month.
Ballarat North, VIC
Following the property’s exclusion from the Ballarat North PSP, a revised valuation was completed which reflected a reduced value. The facility was subsequently adjusted in October 2025 to ensure ongoing covenant compliance.
Mount Cottrell, VIC
The borrower continues to hold the properties as a land bank. The due diligence period on the Oakbank PSP has been completed. The VPA has submitted the 2025/2026 business plan to the Minister for Planning which includes prioritisation of Horizon 2 PSPs. There is potential for the Oakbank PSP to be included in the business plan, while no official timeframe for approval has been provided.
Gungahlin, ACT
The borrower is working to satisfy the outstanding conditions precedent for the refinance. As the current facility has now expired, the loan is in default pending financial close of the new facility.
Sellicks Beach & Gilberton, SA
Newport, NSW
The facility, which expired on 28 July 2025, remains in default with interest capitalising until repayment.
Civil works on site are now complete. The remaining focus is the filtration unit installation and the Ausgrid outage scheduled for December 2025. Title issuance is forecast for late January 2026.
Council issued further feedback on the marina DA on 22 October 2025. Amended plans were lodged on 14 November 2025, with approval anticipated in late January 2026.
Gawler, SA
Across Stages 5–9, more than 90% of lots have been sold. Although the facility only relates to Stages 5–7, sales in Stages 8 and 9 have also been strong, with 100 of 101 lots now contracted.
Civil works for Stages 5–7 continue to progress, with completion expected in Q1 2026.
Munno Para(Smitham Road), SA
Tree stumps have been removed and topsoil stripping is finished. With bulk earthworks now over 90% complete, the site is taking shape.
Shepparton North, VIC
Burpengary, QLD
Construction continues to progress and the latest status of works include:
-
Bulk earthworks are complete
-
Retaining wall installation has commenced
-
Stormwater works are progressing
-
Sewer works have commenced
Due to the initial delays and further weather-related impacts through September and October, Practical Completion (PC) has been pushed out to April 2026. With the current facility expiring on 28 January 2026, the facility will need to be restructured to allow PC to be achieved and settlements to occur. ARK is currently engaging with the Sponsor to finalise the restructure by the end of the year.
Munno Para Downs (Andrews & Hatcher Road), SA
Elizabeth South, SA
Devon Park, SA
Remediation works have now been completed, with all soil and vapour validation returned within required limits and holds auditor sign off. The final report is inb the process of being sent to the EPA for acceptance.
Civil works will be expected to commence before 8 December 25, with a tender price accepted and documentation being finalised.
Cowaramup, WA
The borrower continues to finalise the detailed design and execute the civil works contract to enable the project to progress into the construction phase.
New Farm, QLD
ARK has refinanced the property into a new seven-month facility, providing the sponsor with sufficient time to complete the renovations. These works have already generated value uplift for the property.
Morwell, VIC
Hackney, SA
The project has reached completion, with the Certificate of Occupancy issued on 23 September 2025. Urban Rest has offered to lease the hotel component on a three-year term at $1.2 million per annum, with execution expected by early December.
One of the six Sky Loft apartments has settled, reducing the facility by $3.6 million. A second apartment is sold but remains subject to the purchaser selling their existing home.
The West Lakes property settlement has been delayed to 1 December 2025 due to outstanding site clearance works. The heritage hotel component, sold for $2.5 million and leased to a food and beverage operator, is also scheduled to settle on 1 December.
Following these settlements, the residual LVR is projected to reduce to ~60%. A major bank has issued indicative terms to refinance the hotel at a 65% LVR, targeting settlement on 19 December 2025. The sponsor has also executed a term sheet with ARK for a residual stock facility to support a refinance of the remaining five apartments.
Warragul, VIC
The borrower has received the draft permit conditions however the issuance of the final planning permit has been delayed due to errors in the authority sign-offs, which must be corrected before the permit can be finalised. It is anticipated that the permit will be issued next month.
Windsor & Prahran, VIC
The borrower continues to hold the property as an investment asset.
Mackay, QLD
The borrower continues to work with council in preparation for securing the planning permit.
Athol Park, SA
Development Approval is expected for December with early communications with council having taken place regarding a planning permit. The borrower has commenced online advertising for future factory/warehouses on site.
Waterloo Corner, SA
The engagement report for the code amendment is nearing completion and will be submitted to the Minister for Planning, with approval expected by the end of Q1 2026.
Toowong, QLD
Since reaching financial close, the sponsor continues to work on progressing the planning application.
Gawler Belt, SA
Following financial close in October 2025, the sponsor has continued progressing the planning application, with approval forecast for December 2025.
Morwell & Tatura, VIC
Tatura
-
41 settlements have been completed to the end of October 2025, with Koham Property continuing to market the remaining 17 lots.
-
2 of the larger lots remain unsold in Stage 1.
Morwell
-
Civil works for Stages 1 and 2 are progressing, with practical completion targeted for March and April 2026. Stage 3 is scheduled to follow in May 2026.
-
Presales total 57 lots across Stages 1–3, including seven builder holds, plus a further nine lots in Stage 4.
The facility remains in default, and ARK has reserved its rights from the 7 March 2025 expiry to charge default interest until an acceptable resolution or exit is reached with the borrower.
"*" indicates required fields